Photo Gallery: Ronald McDonald House Vapor Shield Install

Select an image to see a full-size view.

Before Vapor Barrier Installation Begins

A look at the site before vapor barrier installation.

A look at the site before vapor barrier installation.
A look at the site before vapor barrier installation.

Day 1: Installation of Venting Beneath Concrete Floor

Close look at venting conduit that conducts vapors to venting points.
Close look at venting conduit that conducts vapors to venting points.
View of venting conduit placed within the footprint of the building; to eventually be covered by the concrete floor.
View of venting conduit placed within the footprint of the building; to eventually be covered by the concrete floor.

Day 2: Covering Venting Conduit with Sand and Initial Orange Liner

Sand being placed over the venting conduit.
Sand being placed over the venting conduit.
Sand placed and leveled over the venting conduit. The orange liner in the background is being installed over the sand and venting conduit.
Sand placed and leveled over the venting conduit. The orange liner in the background is being installed over the sand and venting conduit.
Orange liner rolled and joined together.
Orange liner rolled and joined together.
Orange liner seams joined together and sealed with asphalt material.
Orange liner seams joined together and sealed with asphalt material.
Overhead view of the vapor barrier installation.
Overhead view of the vapor barrier installation.
Venting conduit covered by sand and connected to a venting pipe that will run through the building's walls and vent into the atmosphere above the roof.
Venting conduit covered by sand and connected to a venting pipe that will run through the building’s walls and vent into the atmosphere above the roof.
Seams and edges joined to the concrete foundation.
Seams and edges joined to the concrete foundation.

Day 3: Covering Orange Liner with Asphalt Material

Covering the entire liner with asphalt material.
Covering the entire liner with asphalt material.
Liner covered with asphalt material.
Liner covered with asphalt material.

Day 4: Testing Vapor Barrier and Second Orange Liner

The vapor barrier is tested using a "smoke test," where smoke is injected through sampling ports (shown in following photos) through the foundation under the vapor barrier. A visual inspection is conducted to detect leaks in the vapor barrier.
The vapor barrier is tested using a “smoke test,” where smoke is injected through sampling ports (shown in following photos) through the foundation under the vapor barrier. A visual inspection is conducted to detect leaks in the vapor barrier.
After passing the "smoke test," a second orange liner is placed over the asphalt coated first orange liner.
After passing the “smoke test,” a second orange liner is placed over the asphalt coated first orange liner.
View of the sampling ports that go through the foundation. The lower port on the right passes under the vapor barrier, while the higher sampling port, seen on both the right and left (above the orange liner), is above the vapor barrier.
View of the sampling ports that go through the foundation. The lower port on the right passes under the vapor barrier, while the higher sampling port, seen on both the right and left (above the orange liner), is above the vapor barrier.
View (looking down) of a completed vent line connected to the venting conduit under the vapor barrier.
View (looking down) of a completed vent line connected to the venting conduit under the vapor barrier.

Day 5: Second Orange Liner Application Continued, and Vapor Sampling Port Completion

Completion of an upper sampling vent port that will be on top of the vapor barrier and under the cement slab of the building. Sand will be poured over this vent pipe, and then concrete will be poured upon the sand.
Completion of an upper sampling vent port that will be on top of the vapor barrier and under the cement slab of the building. Sand will be poured over this vent pipe, and then concrete will be poured upon the sand.
Completed upper sampling vent port on the completed second liner. The liner seams have been sealed with asphalt material. The second liner layer is complete (it is not completely coated with asphalt material like the first liner layer) and sand will be placed on top of this second liner layer, and then concrete will be poured upon the sand.
Completed upper sampling vent port on the completed second liner. The liner seams have been sealed with asphalt material. The second liner layer is complete (it is not completely coated with asphalt material like the first liner layer) and sand will be placed on top of this second liner layer, and then concrete will be poured upon the sand.

Day 6: Second Orange Liner Installed and Seams Sealed

Completed vapor barrier installation. Sand will be put on the vapor barrier and concrete (making the floor of the building) will be poured once other construction work is completed.
Completed vapor barrier installation. Sand will be put on the vapor barrier and concrete (making the floor of the building) will be poured once other construction work is completed.

Last Updated:

Tags:

Back to top