- Denison Mines Tolling Agreement Rev. 3 Relevant to Terms of Stipulated Consent Agreement Docket No. UGW09-03 (09/01/11)—Author: DRC (12 MB)
- DRC Comments Regarding the Denison Mines Phase 2-5 Work Plan Rev. 2.0 (08/25/11)—Author: DRC
- Denison Mines USA Corp. White Mesa Nitrate Investigation Phase 2-5 Work Plan Rev. 2.0 (08/18/11)—Author: Intera for Denison
- DRC Comments Regarding the Denison Mines Phase 2-5 Work Plan Rev. 1.0 (08/11/11)—Author: DRC
- Denison Mines USA Corp. White Mesa Nitrate Investigation Phase 2-5 Work Plan Rev. 1.0 (08/04/11)—Author: Intera for Denison (17 MB)
- DRC Condition Approval Letter Regarding the Revised Phase 2 Detailed Work Plan (07/18/11)—Author: DRC
- Revised Nitrate Investigation Phase 2 Detailed Work Plan and Schedule (07/12/11)—Author: Denison (15 MB)
- DRC Review Comments regarding the Phase 2 Detailed Work Plan and Schedule (07/07/11)—Author: DRC
- Nitrate Investigation Phase 2 Detailed Work Plan and Schedule (06/30/11)—Author: Denison (13 MB)
- Tolling Agreement (Rev. 2) Relevant to Terms of Stipulated Consent Agreement, Docket No. UGW09-03 (06/30/11)—Author: DRC (5 MB)
- DRC Review Comments Regarding the Denison Mines (USA) Corp. Nitrate Investigation Revised Phase 2 to 5 Work Plan (06/23/11)—Author: DRC
- Nitrate Investigation Revised Phase 2 to 5 Work Plan (06/03/11)—Author: Denison (6 MB)
- DRC/DUSA Memorandum of Agreement, Revision 3, regarding URS services to review the DUSA Phase 1 Nitrate Investigation Work Plan, and the Phase 2-5 Nitrate Investigation Work Plan (05/19/11)—Author: DRC
- DUSA Rev. 1, Revised Phase 1 Nitrate Investigation Work Plan (05/13/11)—Author: Denison (43 MB)
- DRC Comments on the DUSA Phase 1 Nitrate Investigation Work Plan (05/11/11)—Author: DRC
- DUSA Revised Phase 1 Nitrate Investigation Work Plan (05/06/11)—Author: Denison (27 MB)
- Tolling Agreement (Rev.1), Relevant to Terms of Stipulated Consent Agreement, Docket No. UGW09-03 (04/28/11)—Author: DRC (2 MB)
- DRC Comments Regarding the DUSA 2/18/2011 Work Plan and Schedule for Supplemental Containment Investigation Report for White Mesa Mill Nitrate Investigation (03/21/11)—Author: DRC
- DUSA/DRC Memorandum of Agreement, Regarding URS Services for the Supplemental Nitrate Investigation Work Plan and Schedule Review (02/28/11)—Author: DRC (6 MB)
- Rev.1 Work Plan and Schedule for Supplemental Nitrate Contaminant Investigation (02/18/11)—Author: Denison (9 MB)
- Work Plan and Schedule for Supplemental Nitrate Contaminant Investigation (02/14/11)—Author: Denison (9 MB)
- Presentation Slides Regarding the Supplemental Nitrate Contaminant Investigation (02/14/11)—Author: Denison (3 MB)
2010
- Tolling Agreement, Relevant to Terms of Stipulated Consent Agreement, Docket No. UGW09-03 (12/20/10)—Author: DRC
- DUSA Response to the 10/5/10 DRC Notice of Additional Required Action (11/15/10)—Author: Denison (6 MB)
- DRC Notice of Additional Required Action (10/05/10)—Author: DRC
2009
- Nitrate Groundwater Contaminant Investigation Report (12/30/09)—Author: Denison (92 MB)
- Stipulated Consent Agreement, Docket No. UGW09-03 (01/28/09)—Author: DRC
- Plan and Schedule for Nitrate Contamination Investigation Report and Groundwater Corrective Action Plan (11/21/08)—Author: Intera for Denison Mines (13 MB)