Depleted Uranium Performance Assessment:
EnergySolutions

Update April 16, 2021

The DU PA has been incorporated with the Federal Cell License Application. See the Federal Cell License Application page.


Revision 2 of Compliance Report

Update July 11, 2014

Revision 2 of the Report, “Utah Low-Level Radioactive Waste Disposal License (RML UT2300249)—Condition 35 Compliance Report,” which includes responses to the Round 3 Interrogatories (as Appendix E) and responses to all other prior Interrogatories. As an aid to the reviewers, attached are redline-strikeout versions of Appendix A and those appendices that have changed since they were last submitted. This is the final submittal from EnergySolutions before the public comment period starts in August 2014.

  • EnergySolutions Transmittal Letter
  • RML UT2300249—Condition 35,Compliance Report—Revision 2, July 8, 2014
  • Final Report for he Clive DU PA Model, Clive DUPA Model v1.2, July 8, 2014
  • Appendices and References to Appendix A
    • Appendices
      • Appendix 1—FEP Analysis
      • Appendix 2—Conceptual Site Mode
      • Appendix 3—Embankment Modeling
      • EPA 2011b.urlAppendix 4—Waste Inventory
      • Appendix 5—Unsaturated Zone Modeling
      • Appendix 6—Geochemical Modeling
      • Appendix 7—Saturated Zone Modeling
      • Appendix 8—Air Modeling
      • Appendix 9—Biological Modeling
      • Appendix 10(I)—Erosion Modeling
      • Appendix 10(II)—Surface Erosion Modeling
      • Appendix 11—Dose Assessment
      • Appendix 12—Decision Analysis (ALARA)
      • Appendix 13—Deep Time Assessment
      • Appendix 14—Development of Probability Distributions
      • Appendix 15(I)—Sensitivity Analysis Methods
      • Appendix 15(II)—Sensitivity Analysis Results
      • Appendix 16—Model Parameters
      • Appendix 17—Quality Assurance Project Plan
      • Appendix 18—Radon Modeling

References

  • 10CFR61
  • 10CFR834
  • 2000, July 19—Whetstone, Western LARW Cell Infiltration Modeling
  • 2007, Dec—Whetstone, Class A South Infiltration and Transport Modeling
  • 2009, Whetstone DU model 10000 years
  • Adrian Brown 1997
  • Albright et al 2002
  • Atmospheric Modeling Appendix
  • Atmospheric Modeling
  • Baes et al 1984
  • Baird et al 1990
  • Beals et al. 2002
  • Bethenfalvay and Dakessian 1984
  • Bingham Environmental 1991
  • Bingham Environmental 1995
  • Bingham Environmental 1996
  • Biological Modeling
  • Black et al 2001
  • Branson et al 1976
  • Brimhall and Merritt 1981
  • Choppin 2000
  • Clark and Tait 1996
  • Class A Design Drawings
  • Class A South-11e.(2) Eng Drawings
  • Claxton 1999
  • Clive DU PA CSM
  • Clive DU PA FEP Analysis
  • Clive DU PA Model v1.0 Final Report
  • Clive PA Model Parameters
  • Clive PA Model User Guide
  • Clive.kmz
  • Cowherd et al 1985
  • Cui and Eriksen 1996
  • Currey et al 1984
  • Decision Analysis
  • Deep Time Assessment
  • DOE 1997
  • DOE 2001
  • DOE 2003
  • DOE 2009
  • DOE Order 5400.5
  • Dose Assessment
  • DUF6-G-G-STU-003 Henson 2006
  • DUF6-UDS-PLN-005 Rev 2
  • Embankment Modeling
  • EnergySolutions 2009
  • Envirocare 2000
  • Envirocare 2004
  • Envirocare 2005
  • EPA 1988
  • EPA 1989
  • EPA 1993a
  • EPA 1993b
  • EPA 1996
  • EPA 1997a
  • EPA 1997b
  • EPA 1999a
  • EPA 1999b
  • EPA 1999c
  • EPA 2000
  • EPA 2001
  • EPA 2002
  • EPA 2004
  • EPA 2005
  • EPA 2008
  • EPA 2009a
  • EPA 2009b
  • Erosion Modeling.
  • ES Quality Assurance Project Plan
  • Fayer 2000
  • Geochemical Modeling
  • Glover et al 1976
  • Hendee 1986
  • Holldobler and Wilson 1990
  • IAEA 2010 – TRS 472
  • ICRP 1983
  • Johnson and Toth 1978
  • Kennedy and Strenge 1992
  • Kerrisk 1987
  • Khire et al 1997
  • Kocher 1981
  • Krupka et al 2004
  • LANL 1997
  • Last et al 2004
  • Meyer et al 1996
  • Millington and Quirk 1961
  • Model Report References—Internet Links.exe
  • Modeling Diffusion in GoldSim
  • Modeling Ionic Diffusion
  • MSI 2010
  • Mualem 1976
  • Neptune 2005a
  • Neptune 2005b
  • Neptune 2006
  • Nielson and Sandquist 2011
  • NRC 1989
  • NRC 1993
  • NRC 1995
  • NRC 2000
  • NRC 2000b
  • NRC 2008
  • NRC Analysis of DU Disposal
  • Nuclear Wallet Cards 7th ed—reformatted
  • Nuclear Wallet Cards 7th ed
  • ORNL-TM-2000-10
  • ORNL-TM-2000-161
  • ORNL-TM-2000-242
  • ORNL-TM-2000-355
  • Paducah GDP.kmz
  • Pavek 1992
  • Pennington 2009
  • PNNL-13421 2003 Transfer Factors
  • Portsmouth GDP .kmz
  • Probability Distributions
  • Reed et al 1996
  • Robertson 1983
  • Rogers et al 1994
  • Sagebrush, 2001
  • Sander 1999 Errata
  • Sander 1999
  • Sandia 2001
  • Saturated Zone Modeling
  • Schaefer 2003
  • Schroeder et al 1994
  • Scism 2006
  • Sensitivity Analysis
  • Serne 2007
  • Smith et al 1997
  • Solubility Unit Conversions
  • Staven et al 2003
  • SWCA 2000
  • SWCA 2011
  • Tilley et al 2008
  • Tomasko 2001
  • Transporting Uranium Oxide
  • UDWR 2009
  • Unsaturated Zone Modeling
  • USFS 2005
  • USFWS 2006
  • USGS 1973
  • Utah Permit UGW450005 current
  • Ward et al 2005
  • Waste Inventory
  • Waste Profile Record SRS DU 9021-33r0
  • Wolfsberg and Stauffer 2003
  • Yu et al 2001
  • Zlatnik 1999a
  • Zlatnik 1999b
  • Zlatnik 1999c
  • Zouhar 2003

GoldSim Installation Files

Be sure to download version 10.5, service pack (SP) 4.

With GoldSim Player one can view, navigate and run GoldSim models (however, one needs the commercial version of GoldSim to create new models and edit existing models).

Links

For further information, contact Charles Bishop ([email protected]), (385) 622-2211.

Back to top